On July 3, the City of Tampa Wastewater Department discovered a wastewater overflow in South Tampa. Before it was fixed, 57,820 gallons of wastewater moved into Tampa Bay.
After a backup at the Bayshore Avenue Pumping Station and a control system failure at the San Carlos Pumping Station, the overflow discharged from the holes at the top of three manholes, then entered nearby stormwater inlets that flow into Hillsborough Bay.
“We had more rain that day than we got during Hurricane Elsa,” Brad Baird, Deputy Administrator of Infrastructure for the City of Tampa, told Creative Loafing Tampa Bay.
Technicians were unable to collect any of the overflow to return it to the wastewater collection system. As required by law, the city reported the event to the Florida Department of Environmental Protection (FDEP).
The overflow lasted from 4:22 p.m.-11:15 p.m. as the thousands of gallons of waste flowed. Warning signs were posted near the overflow site at 2930 W Coachman Ave.
RELATED
The City of Tampa would like you to stop clogging its sewer system with ‘fatbergs’
Baird says the exact cause of the overflow is not known, but most often they are caused by flushable wipes and similar non-flushable materials (aka fatbergs) that cause clogs in piping. He asks people to avoid flushing such materials to avoid backups.
While the backup on Bayshore was the main cause of the overflow, a secondary problem occurred when the control system at the San Carlos Pumping Station in South Tampa failed to switch from smaller to larger pumps during the heavy rains.
Technicians say that after the control system failed, the station was running on back-up pump controllers. The controllers had one common fuse that blew, causing further problems. The technicians rewired the backup to function properly for the rest of the night.
The control system that failed has been rectified, Baird says. A $6.5 million upgrade of the Bayshore Pumping Station is in the works, planned to be completed in June 2023. In the meantime, the city is installing a temporary bypass pump to deal with heavy rains. Adam Smith, Director of Communications for the City of Tampa, sent CL Tampa Bay a “Wet Weather Projects” document which details the city’s multi-million dollar efforts to prevent overflows since 2016. Nine pumping stations across the city are included in the project.
Last week’s overflow occurred just months after the Piney Point environmental disaster in April. The FDEP estimates that about 215 million gallons of polluted water entered Tampa Bay during the event.