Credit: Photo via Duke Energy

Credit: Photo via Duke Energy
State regulators on Tuesday approved requiring Duke Energy Florida to return $16.1 million to customers in a case that stemmed from problems at the utility’s Bartow power plant in St. Petersburg.

The Florida Public Service Commission upheld an administrative law judge’s recommendation that Duke should refund the money.

The case, at least in part, involved allegations that Duke’s predecessor, Progress Energy Florida, operated a turbine at the plant beyond its capacity, leading to later problems that forced a 2017 outage.

Administrative Law Judge Lawrence P. Stevenson in April recommended that Duke return $11.1 million in what are known as “replacement power” costs that were required during the outage.

Also, he recommended that the utility refund about $5 million to cover costs of replacement power needed because the turbine operated below expected levels from 2017 to 2019 after coming back online.

Support local journalism in these crazy days. Our small but mighty team is working tirelessly to bring you up to the minute news on how Coronavirus is affecting Tampa and surrounding areas. Please consider making a one time or monthly donation to help support our staff. Every little bit helps.

Follow @cl_tampabay on Twitter to get the most up-to-date news + views. Subscribe to our newsletter, too.